Positive Train Control: State of the Industry

Positive Train Control (PTC) is an advanced system designed to prevent train-to-train collisions, over-speed derailments, unauthorized incursions into work zones, and train movement through switches left in the wrong position. PTC monitors and, if necessary, controls train movement in the event of human error


With the passage of the Rail Safety Improvement Act in 2008, 41 commuter, Class I freight, and short line railroads were required to install PTC. Also, 60,000 miles of track would need to be equipped with wayside components, and trains that operate over another railroad’s tracks must be interoperable, that is, compatible with the host railroad’s PTC software, which often requires extensive custom engineering and installation. 

Commuter railroads alone will spend an estimated $4.1 billion to achieve full implementation of PTC. While there have been federal grants made available to aid public agencies in implementing PTC, much of these monies were authorized after the first PTC deadline, and still, federal dollars are slow in getting to the grantees. 

At a March 1, 2018 hearing of the Senate Commerce Committee, the DOT Inspector General noted that “nearly $15 million of the $25 million awarded in August 2016 had not been obligated to the grantees. Similarly, out of the $197 million authorized for PTC implementation under the FAST Act, approximately $190 million had not been obligated to the grantees, even though award selections were announced last May [2017].” 

Further, one recipient pointed out that the amount of federal money in PTC-specific grants ($15.8 million) they received was minimal compared to the $310 million in federal and state funds they had to divert to implement PTC. Diverting these funds, however, necessitated a delay in completing state-of-good-repair projects elsewhere in the system. 

In addition, not receiving necessary funding meant a subsequent delay in agencies being able to access the limited number of qualified suppliers and system integrators with the expertise to deliver PTC systems.  

Industry-wide dependence on too few qualified suppliers has eaten away at contingencies built into the implementation timelines of railroads working to deliver PTC by December 2020.  In July 2019, GAO reported that “vendor and software issues are currently major or moderate challenges for PTC implementation….(and) certain software functionality had yet to be developed, tested, and implemented to address reliability issues and facilitate interoperability.”

“The 41 railroads required by Congress to implement positive train control (PTC) systems by December 31, 2018 have submitted documentation that they assert is sufficient to meet the statutory requirements for system activation or the statutory requirements to qualify for an alternative schedule (“extension”) for up to two additional years to complete full implementation.”

You can find the FRA’s quarterly update on railroads’ PTC implementation status here: https://www.fra.dot.gov/app/ptc